|
| |
GLOBAL PLATFORM
DESIGN.
Introduction
Design strategy Small
platforms Medium platforms
Large platforms Previous
page
-
Introduction:
-
- The
traditional platform designs vary from the ultra-small "flag
pole" type of platforms to the really heavy ones with topsides
weight of some 50000 ton. There are fixed platforms and floating
platforms, semi-rigid and tension leg platforms, all made to serve
their different purposes; fighting the budgets as well as ambient
conditions.
-
- Most of the platforms are designed with two main objectives in
mind; low investment cost and sufficient integrity to withstand the
ambient forces, wear and tear.
-
- Since most projects are judged by their potential generated
"cash flow after tax" or Net Present Value (NPV), the focus
is set on factors like investment cost and date of first oil. In order
to accommodate the need of an optimal NPV and low project risk, TRC
has looked into a different platform design strategy.
-
-
If you click on the curve, you can see the importance of reduced investment
cost and first oil on the NPV. Since the NPV is the discounted cash
flow, it is obvious that "money now" has a higher value
than "money later".
-
-
By a click on the curves, you will see indicated high- and low budget cash
flows. Since it is difficult to know the value of the produced oil and
gas during the life cycle of the field, designing the complete
platform for any of these events may increase the project risk and
lower the profit.
- Would it not be wise to select a strategy that proved to be
advantageous for the possible development of the field by making the
production systems, hence the platform more flexible in terms of
adapting to the field production rate and the market cost of the
products ?
- The main issue here is therefore to design the "backbone"
of the platform, the support, strong enough to accept the higher
weight needed for the best case production budget, and to design the
topsides with the flexibility of accepting a rapid and low-cost stepwise increase in
production, accommodate the need for water injection, gas lift, adding
more wells, satellites, etc ?
-
Go to top
-
A new way to look at fixed
platforms.
-
- -
A fixed platform is in fact a "crane" standing on the sea
bed, so why do we need the huge floating cranes to install the
topsides ?
-
- -
If we design the platform topsides support structure with members in
tension rather than members in compression, could we not save structural
weight ?
-
- -
Since the fabrication cost of module- and cellar deck type of
structures is higher than jacket type of structures, why not
let a jacket fabricator make the topsides support structure as an
integrated part of the jacket ?
-
- -
Since parallel activity type of fabrication schedules are more
flexible and time saving than the series-type of schedules used to
day, why not take advantage of that, and save project execution time
as well ?
-
- -
If we use open or closed system cassettes instead of modules, would it not be
relatively easy to increase the production capacity by adding
cassettes ?
-
-
- These
are some of the questions we have made during the process of optimizing
the global platform designs.
-
- TRC
platform
designs and efficient fabrication methods for platforms will reduce initial capital
expenditure, reduce time between project start and first oil, lower
the cost of maintenance, lower the cost of platform- and system
extensions and make the platform and its systems re-usable thus also
considerably improving the project Net Present Value.
-
Go to top
-
The
small PEF platform designs:
-
-
No, this is not a platform, but a portion of a
Stay-Bridge during construction !
You can see two of the stay wires running from the top
of the tower down to the center of the bridge section. The complete span is really suspended in those
stay-wires.
The ultimate load of such a stay bridge wire is close
to 17,100 kN and the specific weight only 85 kg per meter !
The reason for this exercise is obvious, since the way
the bridge was designed, also may help us save structural steel weight
in the platforms.
Take
a look at this platform !
- (Click on the pictures to enlarge.)
-
-
This patented platform design is a typical result of the TRC
development strategy. Look at the topsides. All cassettes are
hanging from the horizontal support truss connected to the platform
legs by stays or cables in tension.
-
-
-
The platform
jacket is fabricated in one piece from the bottom and up to the
stay-bridge like connections to the hanger system that supports the
topsides cassettes. The platform may be installed by using supply
vessels. One proposal is to install a platform template, perform
drilling, and then pull the platform with positive buoyancy down to
the template using lifting jacks fitted to the top of the
jacket.
-
-
The lifting system for the
cassettes is always present, and will lift the cassettes up from a
supply vessel. The cassettes may be installed in the middle of the
platform, or hanging from the support system in two directions.
Cassettes may also be installed above the horizontal support beam
level. All kind of cassettes may b used. On the picture, a combined
living quarter and workshop cassette is temporarily installed during
hook-up or maintenance periods.
-
-
-
The cassettes may easily be
removed and brought onshore by a supply vessel for major
overhaul.
-
- The saving potential in
topsides structural weight is some 70%, and the cost saving abt. 40%
compared to a traditional platform. Further, the platform may be
developed sequentially, or moved to other locations if needed.
-
- If you wish to read more about this particular platform design,
order the CD information package, or look at the PEF platform report.
Advantages:
 | Parallel activities schedule |
 | Shortened project execution time |
 | Very low investment cost |
 | Installation and removal by use of supply vessels only |
 | "Install only what you need" philosophy. |
 | Flexible in terms of stepwise development |
 | Very easy to remove and re-use elsewhere. |
Go to top
-
- The
medium size PEF platform designs:
-
-
This platform topsides design is a hybrid between the integrated
topsides and closed cassette principle. The idea was to design a
platform with a basic production system, but with a built-in option to
install additional two cassettes at a later stage. Since the support
structure was planned to be a GBS, a fully integrated truss system was
proposed as support for the topsides.
-
-
-
The
platform in the foreground is based on the integrated topsides
principle. It has no cellar deck, but the structure contains and
supports fully developed open system cassettes. The main deck area has
been reserved for later installations. Here, the load transfer of one
cassette deck takes place.
-
-
-
As
can be seen from the picture, a system cassette deck is being
installed into one of the topsides compartments.
Advantages:
 | Parallel activities schedule |
 | Shortened project execution time |
 | Low investment cost |
 | Installation and removal by use of supply vessels only |
 | "Install only what you need" philosophy. |
 | Flexible in terms of stepwise development |
Go to top
-
- The
The large PEF platform designs:
-
- There are two particular types
of large integrated topsides platform designs (IPEF). One made for a
PEF type of installation on a steel jacket, and one for GBS type of
platforms.
-
-
-
The integrated topsides on this platform is designed with system
compartments, but as the other designs, the system cassette decks may
be introduced from the underside or horizontally into the structure at
time of assembly or later. The complete topsides may be fabricated
onshore and most of the systems tested before installation on the
jacket. The topsides carry its own lifting equipment, which is
connected to the connecting truss or leg extension of the jacket at
arrival.
-
-
-
The topsides is then
transferred to the lifting system and elevated according to the PEF
method. The topsides may be removed later using the method in
reverse.
-
-
-
The GBS platform adoption of
the fully integrated topsides also take advantage of the strength in
the very high truss system and compartments for the system cassettes
and at the same time benefit from the open access fabrication and
installation principles with a parallel activities type of
schedule.
-
-
-
As may be seen from this
schedule, the system decks may be inserted into the structure very
late in the process, even at-shore, in-shore or offshore. The savings
in structural steel and improvement in fabrication productivity is
very significant.
Advantages:
 | Parallel activities schedule |
 | Shortened project execution time |
 | Fabrication and testing onshore |
 | Reduced offshore hook-up time and cost |
 | Suitable for remote areas or areas with a skimpy infrastructure |
 | Reduced investment cost compared to traditional platforms |
 | Topsides installation and removal by use of barge |
 | Later installation or removal of cassettes by the use of supply vessels |
 | "Install only what you need" philosophy. |
 | Flexible in terms of stepwise development |
Go to top
|