TR Consulting

                                     Double-click on pictures to enlarge.

 

 

Start

Company

Products

Services

News 

Download

 

SUPER-MODULES.

Traditional designs   Why super modules ?   Super module design    Advantages   Previous page

The traditional platforms and modules:

 
 
Rendering of a ttraditional multi- module platform.
 
The traditional platform design is normally made up of the following:
 
- A platform support. ( A steel jacket, concrete or floating). 
- A cellar deck. (A module support frame). 
- A platform topsides (A collection of modules containing various process and utility systems). 
 
The reason for designing the platforms like this, probably has to do with the offshore lifting capacity, i.e. the fact that the offshore cranes could not lift more than the module weight. 
 
The disadvantages are easy to comprehend: 
 
- Too much steel in the cellar deck in order to make a stiff bridge for the modules. 
- Too much structural steel in the modules since they are made as separate units. 
- Too many interface areas between modules. 
- Too much offshore hook-up work. Expensive maintenance and re-building. 

Go to top

Why Super-modules ?

 
The floating crane lifting capacity has been steadily increasing from some 300 ton to 12000 ton, and this has made it more attractive to design platforms with "super-modules". This means that the systems are contained in bigger modules in order to save steel weight and offshore hook-up work. 
 
Rendering of a typical super-module platform topsides. Most super-module platforms still have got a cellar deck, but often 4-5 large modules are used to contain the systems. This also provides a better and more  planned  weight distribution, which in turn makes it possible to save weight also in the cellar deck. 
 
However, one problem remains to be solved, the fabrication of the super-modules. 
These building blocks are some 30 m high, 30 m long and 15-19 m wide with a load-out weight of between 4000 and 6000 ton. The number of fabricators will be limited because of the size and load-out facilities. In addition, the productivity suffers, the project risk is increased and the modules becomes more expensive than one should anticipate, despite the saving in structural steel and reduced hook-up work. 
 
Rendering of a traditional construction method for large multi- deck modules. The reason for this problem is mainly due to the traditional fabrication method, the so-called "stacking method" or the "steel-first then the outfitting" type of schedule. 
 
The stacking method shown on the picture above was for a period the most popular fabrication method. This method was however not suited for the new module size, and the yards got into problems, especially  with decreased productivity, complicated project schedules, dramatic effects of late arriving equipment and changes, long delivery times and rigid project execution plans. 
 
Typical traditional series- activity logical planning network for module building.  Now take a look at the typical fabrication schedule above by clicking on the picture. It is easy to see that the series type of schedule is a direct function of the module fabrication method. Note that most of the activities are on the so-called critical path, meaning that any delay in the activity will effect the project finish date. ( A more comprehensive schedule is found on the TRC demo disk version 1.2.)
 
Yet an other problem is the receipt of long-lead items. As you know, the long lead items are normally equipment like gas turbines, separators, water treatment systems, etc. that pertain to the main deck areas. This means that either the equipment has to be installed early in the building process, or one has to find a way to get them in at a later stage.  
The super- module also imposes problems on the detail planning level, as there will be conflicts between the activities of different trades. Typical problem areas are; sand blasting, fire proofing, painting, instrumentation etc. 
The productivity is also reduced due to the fact that lifting, handling and transport becomes more and more difficult as the module is being built and closed. 

Go to top

The optimized super-module design and fabrication method.

 
To overcome all these problems, TRC has developed and patented a new and very efficient super-module design and fabrication method called the LMEF method.  The method takes advantage of quite a different fabrication schedule, a parallel activities schedule. This makes the project much more flexible to manage, since most of the activities are not on the critical path. The schedule opens up for changes and late arriving equipment without extra cost or delay, and may therefore shorten the total fabrication time.
 
The optimised parallel- activities logical network developed by TRC.
 
The module design and fabrication method is the following:  
 
The module truss systems is fabricated as one complete unit. This may be performed in different ways, but TRC favor the roll-up method shown on the picture below if a huge shed with overhead cranes is not available. 
 
Rendering showing roll-up of the main truss un a super module according to the TRC invention.
 
At the same time, all the module system decks are fabricated with mezzanines etc. The equipment, spools, HVAC, instrumentation etc. is installed on the system decks, which has full open access from above and from all sides. 
 
Rendering showing transport of the finished system cassettes from the yard to the ready module framework.
 
The systems are then tested out and commissioned, and brought to the finished module frame. 
 
The module during insertion and lifting of each individual system deck.
 
The installation of the system decks takes only one day by lifting the decks up from the ground level and fitting them inside the main frame. Then the vertical hook-up and testing remains before the module may be shipped to the platform. 
 
Rendering of a fully integrated topsides designed in accordance with the invented IPEF principles.
 
The LMEF method is also paving the way to the fully integrated topsides platform, IPEF, which may be even more efficient and cost saving.

Go to top

 

 

Advantages:

Significant saving in structural steel
Parallel fabrication schedule
Shortened fabrication time
Flexible in receiving late arriving equipment
Flexible if changes are needed
Full open access to the system decks at all times during fabrication and installation
Accepts a very high worker density without loss of productivity
Deck fabrication may take place in small yards / buildings
Module trusses may be erected in the open without the use of cranes.
Fabrication productivity is improved by 35%
May be used for sequential development in that decks may be introduced offshore.
Very cost-effective.

Go to top

 

TR Consulting, Joh. Falkb.gt. 10, 5538 Haugesund, Norway. Tel: +47 52729124, Fax: +47 52724196, C.E.O. Cell phone.  +47 90 616969  e-mail: trcons@online.no or trcons@start.no